Jingcheng CJD50-FL valve-bag screw packer
Screw-fed valve-bag packing machine with a published 10–50 kg range. Confirm the actual powder/bag trial, full-scale accuracy basis and included handling options.
A screw feeder with operator bag handling
The base machine is not an automatic bagging line.
The official CJD50-FL entry describes variable-frequency screw feeding for powders and granular materials. It names dry powder mortar, calcium carbonate, bentonite, diatomite and other materials as applications. [1] These examples establish supplier-listed uses, not acceptance of every formulation.
- The operator places the bag and triggers the start switch.
- The machine clamps the bag and feeds rapidly.
- As the target approaches, feeding slows for final filling.
- At the set weight, feed stops and the bag mouth is released.
- The operator removes the filled bag and places the next one.
Automatic bag placement and discharge are described as additions for upgrading the semiautomatic machine. Request the exact selected configuration and sequence. No palletiser, closure machine or dust collector is established as standard supplied equipment.
Keep the published values and their qualifiers together
Source values are selection inputs, not platform-tested ratings.
| Item | Published value | Selection qualification |
|---|---|---|
| Materials | Powders and granular materials | Confirm actual flow, particle and bag behaviour by trial. |
| Feed | Variable-frequency screw | Confirm offered screw/configuration and material compatibility. |
| Weighing range | 10–50 kg | Agree each intended target fill and accepted net mass. |
| Packing rate | 2–3 bags/minute | No material/bag/handling trial conditions are supplied. |
| Metering accuracy | ±0.2% F.S | Source qualifies by material uniformity and packing speed; full-scale basis needs definition. |
| Compressed-air source | 0.5–0.7 MPa; 0.1 m³/min | Confirm supply quality, operating demand and connection requirements. |
| Dust-extraction source | −1 kPa; 600 m³/h | Confirm reference point, duct losses and extraction equipment boundary. |
| Electrical supply | AC 380 V + N + E; 50 Hz; 4.8 kW | Do not silently convert for another destination; require electrical review. |
| Reference dimensions | L 1500 × W 900 × H 1350 mm; inlet Ø300 mm | Explicitly reference dimensions; obtain current released drawing and access clearance. |
The source does not give a machine mass, construction-material grade, screw dimensions, certified accuracy class or standard warranty. The photographs do not resolve these omissions; appearance is not a material certificate.
Resolve F.S before converting accuracy into grams
Range, target fill and full scale are different questions.
The site’s ±0.2% F.S wording does not define the full-scale value used for the offered configuration. Do not describe it as ±0.2% of every bag or assign a gram tolerance by assuming 50 kg is the denominator. Ask for the exact measurement basis, conditions and accepted fill result.
OIML R61 addresses automatic gravimetric instruments that produce predetermined fills. [2] Its terminology helps structure a metrology discussion; the listing does not establish OIML certification or an accuracy class for this model.
Trial inputs
Use the actual powder batch, intended production bag and each target mass. Record material condition, settings, feeding continuity and any anti-bridging option.
Trial outputs
Agree how net mass is independently checked, how many fills are evaluated, acceptable variation and complete-cycle timing. Retain the measurement record, not only a video of a filling bag.
Inspect bag integrity, valve condition, spillage and downstream handling as well as weight. A speed result without those checks may not represent acceptable packed product.
A listed utility demand is not a supplied utility system
Approve the installed arrangement before the equipment ships.
- Powder inlet: obtain the current inlet drawing and define hopper, isolation, supply continuity and responsibility for bridging.
- Air: confirm the quoted pressure/flow conditions, treatment requirements and site connection.
- Extraction: agree where the listed negative pressure and airflow are required, who provides the collector/ducting and how the installation is accepted.
- Power: confirm actual wiring, protection, earthing and suitability for the destination supply.
- Access: include bag handling, cleaning, maintenance and safe isolation space outside the reference footprint.
The public “less dust” comparison supplies no exposure test or reference machine. Have the real material and proposed extraction arrangements assessed for the site. No emission, combustible-dust or explosion-protection performance is inferred.
Quote upgrades as changes to the operating boundary
Options need their own drawing and acceptance.
Material and bag options
The source offers electric mechanical anti-bridging for poor-flow materials and an open-bag clamp for using open and valve bags. Confirm the actual powder and bag trials, contact parts and changeover.
Handling options
Automatic discharge can be combined with a belt conveyor; automatic bag placement plus discharge is described as an automation upgrade. Confirm which devices, conveyor and control integration are included.
Ask whether changed options alter dimensions, utilities, weighing behaviour or cycle acceptance. Do not assume the original base-machine figures remain valid for every modified line. Bag closure and product transport after removal should have an explicit owner.
Before contracting, confirm the actual manufacturing/trial site and issuer with Jingcheng; its website manufacturing description and the registered sales/software business scope are distinct records. Commissioning, training, spare seals/contact parts and support terms remain quotation items.
Request a CJD50-FL powder-and-bag trial
Send the intended fill and interfaces with the model.
Sources & review
- CJD50-FL official product entry ↗
Nine original specifications, dry-mortar application, operating sequence and optional configurations.
2026-10-11 - OIML R61-1:2017 scope and terminology ↗
General automatic gravimetric-filling measurement context; not CJD50-FL certification.
2026-10-11
Specifications come from the manufacturer’s published information and the sources above; buying advice is written by CivilEquip with AI assistance. Ask the manufacturer to confirm the data for your configuration. Editorial policy · Report a correction.